Telstra continues Small Cells rollouts as part of Mobile Black Spots Program


Back in February, Telstra announced that they had turned on the 300th site as part of Federal Government’s Mobile Black Spots Program. The announcement said:

With hundreds of new base stations, small cells and site upgrades built over the last 6 months or scheduled around the country during the next 6 months, this financial year (FY18) is shaping up as a big year for expanding mobile coverage for regional Australia.

Then in March, it installed 4G small cells at 50 sites across the Melbourne CBD as part of a national three-year rollout of 1000 cells intended to boost capacity. As per RCR Wireless, Telstra’s small cell program stipulates the deployment of 1,000 small cells in metro and regional locations within the next three years. Some of these areas include Sydney, Brisbane, Adelaide and Perth.

Finally, another announcement in March indicated that Telstra is trialing small cells on Tasmania’s power poles to fix mobile black spots. As per this announcement:

We have announced we will trial the installation of small cell mobile technology on TasNetworks‘ electricity distribution infrastructure to help fill some of Tasmania’s mobile black spots.

The small cells trial will begin with a single site in the Weldborough area, where a small cell installed on TasNetworks infrastructure will provide new mobile voice and broadband coverage.

With the construction of a standard mobile base station typically costing several hundreds of thousands of dollars, small cells may allow us to deliver mobile coverage and capacity to smaller communities and areas where the construction of a mobile base station would otherwise be uneconomical.

The trial will test the feasibility of using existing TasNetwork power poles to improve mobile coverage in parts of Tasmania.